About Us
The Benton County Solid Waste Disposal Commission
In 2013, Benton County’s Landfill was nearing its design capacity, and this motivated
residents from across the county to meet to discuss the future of landfill operations in the
County. These initial meetings led to the formation of an “ad-hoc” Committee - composed
of elected officials, and both urban and rural residents from across the County - to direct the
future of Solid Waste Management inside the County.
The newly formed committee decided to re-create the Benton County Solid Waste Disposal
Commission (BCSWDC), a commission initially created in the mid 70’s to build & manage
the county’s landfill; the original commission would later turn over control of landfill
operation to the county’s supervisors.
On July 1st of 2014, a revised “28E” Agreement between the Cities and the County,
created the new Benton County Solid Waste Disposal Commission.
After considering all options, the BCSWDC decided the County should remain a landfill
operation at its current location; this required the immediate construction of a new waste
cell. Barker/Lemar Engineering was hired to design and supervise construction of Cell G,
and on April 21, 2015, J B Holland was awarded the contract. Construction began in late
July and was completed in October.
On February 18, 2016, a proposal from Schrader Construction was accepted to connect
the ground-water drainage system of the landfill, tying the original cell’s drainage pipes to
the new waste cell’s drainage system. The work was completed in March, bringing an
end to the construction of Cell G.
In early August of 2016, work started on a new maintenance building, capable of housing
and maintaining the Landfill’s large equipment, it was finished in late October of 2016.
In September of 2018, a new scale house was built, and in the Fall of 2022 work began on
our “Convenience Center” to expedites and simplifies a customer’s Trip to the Landfill.
Design work for a new Waste Cell (View Cell H Construction) and Sediment Basin was
completed by HLW Engineering Group in late 2022. Bids were solicited, and a contract
for the work was let on February 16, 2023, to J B Holland. Construction started 1n June
and on October 9th, the Landfill was given approval by the DNR to start using the cell.
In February of 2025, HLW Engineering Group completed its design work for relocating
the existing lagoon, to help in finalizing the long-term operational layout of the Landfill;
on March 20, 2025, the Commission accepted a Bid from Connolly Construction, Inc. to
proceed with the project.
28E Agreement:
BCSWDC By Laws:
Cell G and Sediment Basin
Permitted Landfill Expansion
Convenience Center
Site of Lagoon Relocation