About Us
The Benton County Solid Waste Disposal Commission
In 2013, the Landfill in Benton County was nearing its designed capacity, this motivated
residents from across the County to meet to discuss the future of landfill operations in the
county. The initial meetings led to the formation of an “ad-hoc” Committee - composed of
city and rural residents, along with elected officials from across the County - which was tasked
with the job of directing future Solid Waste Management in the County.
The newly formed committee decided to re-create the Benton County Solid Waste
Disposal Commission (BCSWDC), a commission originally created in the 70’s to construct
and manage the County’s Landfill; the original Commission would eventually turned
control of Landfill operation over to the County’s Supervisors.
On July 1st of 2014, a revised “28E” Agreement between the Cities and the Supervisors
of Benton County, created the new Benton County Solid Waste Disposal Commission;
a revised set of By-Laws for the Commission was also adopted.
After looking at all available options, the BCSWDC decided that the County should stay a
landfill operation at its current location; this required the immediate construction of a new
waste cell.
To design and supervise construction of a new waste cell (Cell G), the Commission hired
Barker/Lemar Engineering. On April 21, 2015, J B Holland was awarded a contract to
build the new cell, and construction began on July 27th and was completed in October.
On February 18, 2016, a proposal from Schrader Construction was accepted to connect
the ground-water drainage system of the landfill, tying the original cell’s drainage pipes to
the new waste cell’s drainage system. The work was completed in March, bringing an
end to the construction of Cell G.
In early August of 2016, work started on a new maintenance building, capable of housing
and maintaining the Landfill’s large equipment, it was finished in late October of 2016.
In August of 2018, the Landfill’s Lagoon’s capacity was expanded, and one month later a
new scale house was completed.
In the Fall of 2022 work began on our “Convenience Center” that simplifies and speeds
up our customer’s Trip to the Landfill.
Design work for a new Waste Cell (View Cell H Construction) and Sediment Basin was
completed by HLW Engineering Group in late 2022. Bids were solicited, and a contract
for the work was let on February 16, 2023, to J B Holland. Construction started 1n June
and on October 9th, the Landfill was given approval by the DNR to start using the cell.